Chalmers Street Substation - Transport NSW

Have a question?
Need assistance?

Have a similar project that you need assistance with? Complete the form below and one of our Heritage assessment specialists will be in touch as soon as possible.

  • This field is for validation purposes and should be left unchanged.
By signing in you agree with the Terms and Conditions and Privacy Policy

Professional Associations

About the project
Key Details
  • About The Project

    Heritage design advice, liaison with the construction team, taking charge of all lodgements to OEH and liaised with sub- contractors including electrical, fire, hydraulic, mechanical, etc. for the existing 1920s sub- station and selection of materials and finishes for the new sub- station.

  • Summary

    Heritage 21 was commissioned by Beca Consulting Engineers to participate in all stages of the construction of a new electrical sub-station at the Charmers Street end of Central Station in Chippendale, NSW. This commission spanned the entire range of consultant input including heritage design advice, detailed documentation, site induction and participation throughout the construction phase. The work included the repurposing of the existing sub-station building that was constructed in the 1920s. This building was surveyed in detail by Heritage 21 to find appropriate new uses for the building.

  • What was done

    A new sub-station building was constructed close to the existing sub-station building- the later being heritage listed in accordance with the CMP that was prepared by Heritage 21. Many services had to run from the new sub-station into the old building and it was Heritage 21’s job to ensure that no damage was sustained to any heritage fabric in the three buildings- Prince Alfred substation, switching house and compressor house.

  • Time frame

    Approximately 4 years from design to construction completion.

Services provided
  • Conservation Management Plan
  • Numerous Statements of Heritage Impact.
  • Liaison with Sydney Trains
  • Working closely with RCC and Abergeldie (contractors)
  • Temporary Protection Plan
  • Interpretation Strategy
  • Schedules of Fabric Significance
  • Presiding over all applications to the consent authority for changes, variations, etc.
  • On-site Heritage Architect
Why was the work undertaken?

Sydney Trains determined that an additional electrical sub-station would be required to run the trains in accordance with a major rail network expansion throughout metropolitan Sydney.

Who was the work completed for?

Mainly for RCC and Abergeldie Contractors, but also for Sydney Trains indirectly. Heritage 21 also worked closely with Becca Engineers, GHD and Amac Archaeologists.

Outcome

A successful project for the ongoing use and improvement of the metropolitan rail network and complete protection and conservation of the three heritage items on the site being the Prince Alfred substation, switching house and compressor house.

View gallery Get in touch

What our clients
& partners say:

“'I have had some involvement with Heritage 21 in working through the design and documentation currently taking place at the Exchange Hotel in Balmain, and have appreciated the ability to provide recommendation on potential design outcomes that are able to be supported as consistent with heritage requirements' ”

Liam Corr
Registered Architect

“It has also been a pleasure working with Paul and your team on this project. To be honest, I had not done heritage projects before and it was only through Paul and your team’s guidance that allowed me to complete this project at a high standard. I am now confident in doing heritage projects like this and I look forward to the next project that we can work on together. Again, thank Paul and Divya patience and professional advice throughout the process. ”

Eddie Lam
Builder

“Really appreciate the help in responding the RFIs. I acknowledge all the work that was required and that you put into that report. Maddocks said you made their job easy! ”

Max Symonds
Development Manager - Metro Property Development

“Just as client-side project manager for Honey Insurance, I would to let you know that it has been a very positive experience and appreciate your quick responses and quality of work from you and your organisation thus far. ”

Nick Maric
Project Management

“I just wanted to share the good news that Canterbury-Bankstown Council has decided to withdraw the development control order issued to our client. The report you prepared was pivotal in this decision by the Council. Many thanks to you, Paul and the team for your work on this. ”

Anna Lindeman-Jones
Senior Associate - Addisons

“I'd like to thank Paul and Lauren for their dedication, persistence and well thought through support and substantiation of the design merits of our development proposal; it is no easy feat to have a new building approved in a heritage conservation area, and particularly adjacent to heritage items. ”

Tim McLachlan
Development Manager

“I consider that we have a well prepared case that has been cogently articulated by Paul and Michael. It is a fraught experience for us, however we do appreciate the input from top professionals such as Paul ”

Richard Mann
Registered Architect

“Hi team at Heritage 21 I just wanted to say thanks for all your hard work on Mosman and being so responsive etc. One of our team recommended you and I have been very happy with the service provided. ”

Di Jones
Principal - Linked Project Management

“We would also like to take a quick moment to thank you all for your contribution to the project and we will update you on any developments as necessary”

Jose Serrao
Registered Architect

“Dear Heritage 21 team, I am please to advise that all the work prepared by your team has satisfied council’s contentions. We definitely know who to come to next time for heritage matters. ”

Andres Caceres
Level 33

“Thank you for all your work preparing this Statement of Heritage. I sat down yesterday and had a good read cover to cover, and felt very appreciative of your level of research and detailed consideration of our requirements.”

Veechi
Varuna', Katoomba

“Just wanted to let you know, Council agreed with us in our application to reinstate the front facade! I am so excited. I wanted to thank you for all your help in getting this across the line. ”

Jane Frawley

“It has been a pleasure to work with you and your team as well!”

Georgia
Holding Redlich

“Dear Heritage 21 team - This is an excellent result, thank you for all your work.”

Sevda Cemil
Midson

“Sites with heritage values present great opportunities, however often can be easily derailed if clear, concise and timely advice is not provide at the earliest stages of site planning. I have worked with Heritage 21 over numerous projects across Sydney and have found them to be valuable project partners in the development process. ”

Vince Hardy
Urban Planning Consultant, Cityscapeplanning+projects

Related
Case studies.

Path-2-rev Group%204%20Copy Group%204
Need help getting started?

Check out our guides.

article-1
Heritage – are we losing the battle?

Since the robust days of the 1970s and the 1980s during which NSW governments and councils committed wholeheartedly and enthusiastically…

Read more
article-1
Five things you need to know about cultural built heritage

Having worked in the heritage space for the better part of thirty years, I have come to rely upon five…

Read more
article-1
Incentivising Ownership of Heritage Buildings

In response to the recent enquiry by the government relating to the NSW Heritage Act, I made the following recommendation.…

Read more

526dad159320ae83e6a08364079da7b7a1b6ece0

Complete the form below to contact us today.

  • This field is for validation purposes and should be left unchanged.
By signing in you agree with the Terms and Conditions and Privacy Policy